File #: 2022-244    Version: 1 Name: Windy Hill Project Manager
Type: Authorization Status: Agenda Ready
File created: 4/29/2022 In control: City Council
On agenda: 5/2/2022 Final action: 5/2/2022
Title: Authorization to allow Croy Engineering (200 Cobb Parkway North, Building 400, Suite 413, Marietta, Ga) to manage the day to day construction and inspection for the Windy Hill Boulevard Project for a period of one calendar year, to begin May 2022 and expire April 2023 in the amount not to exceed $422,920.00, to be funded from SPLOST 2016, which will cover the cost of a Senior Professional 2 and a Construction Manager for that one year time frame and authorize the Mayor to sign and execute all related documents. Ward 3 / Councilmember Lindley Ward 5 / Councilmember Wilkinson
Attachments: 1. Issue Sheet 2022-244 - Windy Hill Project Manager.pdf, 2. Construction Inspection Proposed Resource Allocation.pdf

Impact

WARD / COUNCILMEMBER:  Ward 3 / Councilmember Lindley

                                                                                           Ward 5 / Councilmember Wilkinson

 

$ IMPACT: not to exceed $422,920.00

 

Title

Authorization to allow Croy Engineering (200 Cobb Parkway North, Building 400, Suite 413, Marietta, Ga) to manage the day to day construction and inspection for the Windy Hill Boulevard Project for a period of one calendar year, to begin May 2022 and expire April 2023 in the amount not to exceed $422,920.00, to be funded from SPLOST 2016, which will cover the cost of a Senior Professional 2 and a Construction Manager for that one year time frame and authorize the Mayor to sign and execute all related documents.

Ward 3 / Councilmember Lindley

Ward 5 / Councilmember Wilkinson

Body

ISSUE AND BACKGROUND

The Windy Hill Boulevard Project has required additional time and resources, especially the last two years, and City staff is no longer able to provide the dedicated time and effort the project needs for proper management and inspection. Therefore, the City would like to enter into a one year contract with Croy Engineering to allow them to manage the day to day construction and inspection for this project at a cost not to exceed $422,920.00 to be funded from SPLOST 2016, and to cover the cost of a Senior Professional 2 and a Construction

 

RECOMMENDATION / REQUESTED ACTION:  Public Works staff and the City Engineer recommend authorization to allow Croy Engineering (200 Cobb Parkway North, Building 400, Suite 413, Marietta, Ga) to manage the day to day construction and inspection for the Windy Hill Boulevard Project for a period of one calendar year, to begin May 2022 and expire April 2023 in the amount not to exceed $422,920.00, to be funded from SPLOST 2016, which will cover the cost of a Senior Professional 2 and a Construction Manager for that one year time frame and authorize the Mayor to sign and execute all related documents.