File #: 2022-178    Version: 1 Name: Ardito Construction RFQ Award - Dunn Street Improvements
Type: Bid/RFP Award Status: Passed
File created: 3/21/2022 In control: City Council
On agenda: 4/18/2022 Final action: 4/18/2022
Title: Approval to award RFQ 22-031 for Dunn Street Drainage Improvements to Ardito Construction Company, 1290 Austell Road, Marietta, Georgia, 30080, in the amount of $138,000.00 to be paid out of Water CIP Storm fund. Ward 6 / Mayor Pro Tem/Councilmember Gould
Attachments: 1. Issue Sheet 2022-178 Dunn Street Drainage RFQ Award.pdf, 2. RFQ 22-031 Letter of Recommendation.pdf, 3. RFQ 22-031 Bid Tab.pdf, 4. RFP 22-031 Request for Proposal.pdf, 5. RFP 22-031 Bid Packet - Ardito Construction.pdf

Impact

WARD / COUNCILMEMBER:  Ward 6 / Mayor Pro Tem/Councilmember Gould

 

$ IMPACT:  $138,000.00

 

Title

Approval to award RFQ 22-031 for Dunn Street Drainage Improvements to Ardito Construction Company, 1290 Austell Road, Marietta, Georgia, 30080, in the amount of $138,000.00 to be paid out of Water CIP Storm fund.

Ward 6 / Mayor Pro Tem/Councilmember Gould

Body

ISSUE AND BACKGROUND

The City of Smyrna requested bids for the installation of approximately 477 LN. FT. of 18" HDPE and 33 LN. FT. of 18" RCP storm sewer piping including manholes, road cuts, patching, junction boxes and haul off on Dunn Street in Smyrna. Eight (8) contractors submitted, and the lowest responsive, responsible bidder is Ardito Construction Company, Inc. in the amount of $138,000.00. Please see bid results below.

 

Bidder                                                                                                                                                   Bid Bond                     Acknowledgements                                          Bid Amount

N.S.E.W. Inc.                                                                                                                                                                                                                                                     $70,548.22

Ardito Construction Company, Inc.                                          X                                          X                                                                                    $138,000.00 

Backbone Infrastructure, LLC                                                               X                                          X                                                                                    $193,300.41

Zaveri Enterprises, Inc.                                                                                    X                                          X                                                                                    $212,691.00

Summit Construction & Development, LLC                     X                                          X                                                                                    $213,935.36

Helix Group Inc.                                                                                                         X                                          X                                                                                    $232,971.82

Tople Construction & Engineering, Inc.                                          X                                          X                                                                                    $287,757.00

K.M. Davis Contracting Co. Inc.                                                               X                                          X                                                                                    $302,500.00

 

It is the recommendation of Purchasing and Public Works that this project be awarded to the lowest responsive and responsible bidder, Ardito Construction Company, Inc.

 

RECOMMENDATION / REQUESTED ACTION:  Approval to award RFQ 22-031 for Dunn Street Drainage Improvements to Ardito Construction Company, 1290 Austell Road, Marietta, Georgia, 30080, in the amount of $138,000.00 to be paid out of Water CIP Storm fund and authorize the Mayor to sign and execute all related documents.