Title: Approve request for the road closure at San Fernando Drive intersection on the North side of Windy Hill Road beginning November 6th 2020 thru November 23rd 2020 as requested by Baldwin Paving Company for the construction of a temporary road for a lane shift on the Windy Hill Boulevard Project Weather Permitting.
Attachments: 1. Detour 1 from San Fernando to OldSprings Road.pdf, 2. Issue Sheet 2020-422 Road Closure.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Impact

WARD / COUNCILMEMBER:  Ward 5 / Councilmember Wilkinson

 

$ IMPACT

 

Title

Approve request for the road closure at San Fernando Drive intersection on the North side of Windy Hill Road beginning November 6th 2020 thru November 23rd 2020 as requested by Baldwin Paving Company  for the construction of a temporary road for a lane shift on the Windy Hill Boulevard  Project Weather Permitting.

 

Body

ISSUE AND BACKGROUND

Baldwin Paving the Contractor for the Windy Hill Boulevard project has requested a road closure at San Fernando Drive intersection on the North Side of Windy Hill Road beginning November 6th 2020 thru November 23, 2020 weather permitting for the construction of a temporary road for the lane shift on the Windy Hill Boulevard project. 

 

RECOMMENDATION / REQUESTED ACTION: Public Works and Croy Engineering recommend the approval of a road closure at San Fernando Drive intersection on the North side of Windy Hill Road beginning November 6th 2020 thru November 23rd 2020 weather permitting as requested by Baldwin Paving Company for the construction of a temporary road for a lane shift on the Windy Hill Boulevard project.